Style of Case
In the Matter of the Application of Spire Missouri Inc. d/b/a Spire for a Certificate of Convenience and Necessity to Construct, Install, Own, Operate, Maintain, and Otherwise Control and Manage a Natural Gas Distribution System in Christian County, Missouri as an Expansion of its Existing Certified Areas
Subject Company
Events
| Responsible Party | |||||
|---|---|---|---|---|---|
| 7/20/2026 | Recommendation(s) |
|
The Staff of the Commission shall file a Recommendation no later than July 20, 2026. | ||
| 7/20/2026 | Response(s) |
|
Any other responses shall be filed no later than July 20, 2026. | ||
| 6/22/2026 | Recommendation(s) |
|
No later than June 22, 2026, Staff shall file a recommendation regarding Spire’s application or a status report | ||
| 5/11/2026 | Application(s) to Intervene |
|
Any person wishing to intervene in this matter shall file an application to intervene no later than May 11, 2026 |