Current Date/Time: 7/25/2026 11:26:44 AM
Calendar Display
SR-2026-0305
SR-2026-0305
Submission No.
SR-2026-0305
(Closed)
Style of Case
In the Matter of Missouri-American Water Company's Request for Authority to Implement a General Rate Increase for Sewer Service Provided in Missouri Service Areas
Subject Company
Events
| Responsible Party | |||||
|---|---|---|---|---|---|
| 8/3/2026 | Response(s) |
|
Any responses to Missouri-American’s proposed future test year are due no later than August 3, 2026 | ||
| 8/3/2026 | Filing(s) |
|
The parties shall file a joint proposed procedural schedule no later than August 3, 2026 | ||
| 7/21/2026 | Procedural Schedule |
|
By July 21, 2026, the Staff of the Commission shall file a proposed joint procedural schedule with an evidentiary hearing ending no later than April 1, 2027. | ||
| 7/21/2026 | Response(s) |
|
Any responses to Missouri-American’s proposed consolidation and future test year must be filed no later than July 21, 2026. | ||
| 7/17/2026 | Application(s) to Intervene |
|
Any entity, group, or person wishing to intervene shall file an application no later than July 17, 2026. |