Current Date/Time: 10/26/2025 9:10:23 AM
Calendar Display
GR-2022-0136
Submission No.
GR-2022-0136
(Closed)
Style of Case
In the Matter of Spire Missouri, Inc. d/b/a Spire (West) Purchased Gas Adjustment (PGA) Tariff Filing
Subject Company
Events
| Responsible Party | |||||
|---|---|---|---|---|---|
| 6/3/2024 | Recommendation(s) |
|
Staff shall file a recommendation concerning the above-referenced tariff sheet no later than June 3, 2024. | ||
| 6/3/2024 | Response(s) |
|
Any other responses concerning Spire’s tariff sheet or Staff’s recommendation shall be filed no later than June 3, 2024. | ||
| 5/20/2024 | Report(s) |
|
Staff shall file a status report no later than May 20, 2024, if a settlement agreement has not been filed by that date. | ||
| 3/30/2024 | Data Request Response Time is 5 Business Days |
|
|||
| 3/29/2024 | Testimony |
|
Surrebuttal Testimony - All Parties | ||
| 3/7/2024 | Conference (Hearing) |
|
Settlement Conference | ||
| 3/2/2024 | Data Request Response Time is 10 Business Days |
|
|||
| 3/1/2024 | Testimony |
|
Rebuttal Testimony - All Parties | ||
| 11/8/2023 | Conference (Hearing) |
|
Settlement Conference | ||
| 8/8/2023 | Conference (Hearing) |
|
Settlement Conference | ||
| 6/28/2023 | Procedural Schedule |
|
Joint Proposed Procedural Schedule | ||
| 5/22/2023 | Procedural Schedule |
|
Joint Status Report or Proposed Procedural Schedule | ||
| 3/20/2023 | Procedural Schedule |
|
Joint Proposed Procedural Schedule | ||
| 2/14/2023 | Pleading |
|
Staff Pleading | ||
| 1/19/2023 | Response(s) |
|
Response to Staff recommendation | ||
| 12/15/2022 | Recommendation(s) |
|
Staff Recommendation | ||
| 11/22/2021 | Comment(s) |
|
Any Other Comments | ||
| 11/19/2021 | Recommendation(s) |
|
Staff Recommendation |