Calendar Display
EA-2024-0292
Submission No.
Style of Case
In the Matter of the Application of Evergy Missouri West, Inc. d/b/a Evergy Missouri West for Permission and Approval of Certificates of Convenience and Necessity Authorizing It to Construct, Install, Own, Operate, Manage, Maintain and Control Two Solar Generation Facilities
Events
| Responsible Party | |||||
|---|---|---|---|---|---|
| 6/5/2025 | Objection(s) |
|
Any objections to the agreement filed by the Signatories on May 29, 2025, shall be filed no later than June 5, 2025. | ||
| 5/23/2025 | List(s) |
|
No later than May 23, 2025, each party shall file its list of exhibits. | ||
|
5/22/2025
9:00 AM to 11:00 AM |
Conference (Hearing) |
|
Settlement Conference (location and time TBD) |
200 Madison Street Jefferson City, MO |
WebEx |
| 5/21/2025 | Statement(s) |
|
Position Statements | ||
| 5/20/2025 | List(s) |
|
List of Issues, Order of Witnesses, Order of Opening Statements, and Order of Cross Examination | ||
| 5/19/2025 | Testimony |
|
Surrebuttal | ||
| 5/19/2025 | Data Request Response Time is 5 Business Days |
|
|||
| 5/7/2025 | Testimony |
|
Rebuttal | ||
| 5/7/2025 to 5/19/2025 | Data Request Response Time is 10 Calendar Days |
|
|||
| 4/18/2025 | Response(s) |
|
OPC shall have until April 18, 2025, to file its response to Staff's Recommendation. | ||
| 4/17/2025 | Recommendation(s) |
|
No later than April 17, 2025, Staff shall file a recommendation regarding Evergy Missouri West’s application or a status report stating when it expects to file a recommendation. | ||
| 4/17/2025 | Report(s) |
|
No later than April 17, 2025, Staff shall file a recommendation regarding Evergy Missouri West’s application or a status report stating when it expects to file a recommendation. | ||
| 3/24/2025 | Response(s) |
|
No later than March 24, 2025, Staff shall file a response to Evergy Missouri West’s Response to Staff’s Motion for Extension and the Commission’s Sua Sponte Order Granting Staff’s Motion for Extension | ||
| 3/17/2025 | Recommendation(s) |
|
No later than March 17, 2025, Staff shall file a recommendation regarding Evergy Missouri West’s application or a status report stating when it expects to file a recommendation. | ||
| 3/17/2025 | Report(s) |
|
No later than March 17, 2025, Staff shall file a recommendation regarding Evergy Missouri West’s application or a status report stating when it expects to file a recommendation. | ||
| 12/16/2024 | Recommendation(s) |
|
Staff shall file a recommendation regarding the application, or a status report stating when it expects to file a recommendation, no later than December 16, 2024. | ||
| 12/16/2024 | Report(s) |
|
Staff shall file a recommendation regarding the application, or a status report stating when it expects to file a recommendation, no later than December 16, 2024. | ||
| 11/13/2024 | Application(s) to Intervene |
|
Applications to intervene in this matter shall be filed no later than November 13, 2024. |