Current Date/Time: 10/26/2025 4:13:01 AM
Docket Sheet
GO-2020-0230
Status
Closed (6/8/2020)
Utility Type
Gas
Type of Case
Infrastructure Replacement Surcharge (ISRS)
Subject Companies
Style of Case
In the Matter of the Application of Spire Missouri, Inc. d/b/a Spire to Change its Infrastructure System Replacement Surcharge in its Spire Missouri West Service Territory
Assigned Judge
- Graham, Paul (Lead Judge)
Assigned Attorney
- Berlin, Bob (Lead Attorney)
- Bretz, Karen
Related Submission No.
Consolidated To
Consolidated From
Data Request Contact Person
Selinger, Wes - Data Request - Spire (Gas) (Investor)
Display Items:
-
Filter by Type of Filing:
Show Only:
or Hide:
Returning
38
/ 38
| Filed on Behalf of | Response to Previous Filings | ||||
|---|---|---|---|---|---|
| 38 |
6/8/2020
2:52 PM
|
Notice | Notice Closing File | ||
| 37 |
5/15/2020
3:16 PM
|
Order | Order Approving Compliance Tariffs | ||
| 36 |
5/15/2020
10:13 AM
|
Staff Recommendation | Staff Recommendation for Approval of Spire's Compliance Tariff Sheets | 34 | |
| 35 |
5/14/2020
10:18 AM
|
Order | Order Requiring Expedited Filing | ||
| 34 |
5/13/2020
7:32 PM
|
Motion | Motion for Expedited Treatment (Tariff Revision YG-2020-0198) | 33 | |
| 33 |
5/13/2020
11:35 AM
|
Order | Order Approving Stipulation and Agreement | ||
| 32 |
5/3/2020
4:04 PM
|
Other | Response to Staff in Support of Unanimous Stipulation and Agreement | 31 | |
| 31 |
4/28/2020
2:02 PM
|
Response to Order | Verified Response to Order Directing Filing and in Support of Unanimous Stipulation and Agreement | 30 | |
| 30 |
4/21/2020
4:14 PM
|
Order | Order Directing Filing | ||
| 29 |
4/17/2020
9:33 AM
|
Order | Order Suspending Procedural Orders and Cancelling Hearings | ||
| 28 |
4/16/2020
2:22 PM
|
Joint Motion | Joint Motion to Suspend Procedural Schedule | ||
| 27 |
4/16/2020
2:20 PM
|
Stipulation and Agreement | Unanimous Stipulation and Agreement | ||
| 26 |
4/14/2020
3:45 PM
|
Order | Second Supplemental Procedural Order | ||
| 25 |
4/10/2020
2:57 PM
|
Other | Response of Spire Missouri Inc. to Staff and OPC Recommendations | 21 , 22 | |
| 24 |
4/7/2020
3:15 PM
|
Order | Supplemental Procedural Order | ||
| 23 |
4/6/2020
10:58 AM
|
Request | Joint Request Regarding Additional Procedural Matters | 20 | |
| 22 |
4/3/2020
4:35 PM
|
Staff Recommendation | Staff Recommendation | 11 | |
| 21 |
4/3/2020
4:28 PM
|
Response to Order | The Missouri Office of the Public Counsel's Recommendation Regarding Spire Missouri's Application to Change it's Infrastructure System Replacement Surcharge | 15 | |
| 20 |
3/31/2020
3:19 PM
|
Order | Procedural Schedule | ||
| 19 |
3/26/2020
11:31 AM
|
Procedure Schedule | Proposed Procedural Schedule | ||
| 18 |
3/19/2020
4:38 PM
|
Order | Order Requiring Filing | ||
| 17 |
3/18/2020
11:50 AM
|
Other | Updated Appendices through February 2020 | ||
| 16 |
2/20/2020
10:37 AM
|
Order | Order Concerning Physical Property | ||
| 15 |
2/18/2020
9:41 AM
|
Order | Order Directing Notice, Setting Intervention Deadline, Directing Filing, and Suspending Tariff Sheets | ||
| 14 |
2/14/2020
2:21 PM
|
Response | Response Regarding Spire Missouri Inc's Request for Waiver of the 60 day Notice Provisions of Commission Rule 20 CSR 4240-4.017(1) | ||
| 13 |
2/13/2020
3:50 PM
|
Response to Order | Response to Commission's February 13 Order Directing Filing | 9 | |
| 12 |
2/13/2020
3:39 PM
|
Application | Corrected, Verified Application and Petition of Spire Missouri, Inc. to Change its Infrastructure System Replacement Surcharge for it's Spire Missouri West Service Territory | 8 | |
| 11 |
2/13/2020
3:24 PM
|
Tariff | Tariff Revision (YG-2020-0140) | 8 , 9 | |
| 10 |
2/13/2020
9:47 AM
|
Ex Parte Notice | Notice of Ex Parte Contact | ||
| 9 |
2/13/2020
9:43 AM
|
Order | Order Directing Filing | ||
| 8 |
2/11/2020
4:52 PM
|
Motion | Motion to Reject Tariff Sheets Contained in Application Appendices for Failure to Comply with Commission Rules 20 CSR 4240-40.085(3) & (4) | ||
| 7 |
2/11/2020
3:35 PM
|
Response to Order | Response to Order Directing Filing | 5 | |
| 6 |
2/6/2020
12:02 PM
|
Entry of Appearance | Entry of Appearance (Bockstruck) | ||
| 5 |
2/5/2020
11:35 AM
|
Order | Order Directing Filing Concerning Physical Evidence Lodged with the Commission’s Data Center and Evidentiary Foundation Issues | ||
| 4 |
2/4/2020
10:23 AM
|
Order | Order Setting Time for Responses | ||
| 3 |
2/3/2020
4:21 PM
|
Testimony | Direct Testimony of Timothy H. Goodson | ||
| 2 |
2/3/2020
4:20 PM
|
Application | Verified Application and Petition of Spire Missouri, Inc. to Change its Infrastructure System Replacement Surcharge for it's Spire Missouri West Service Territory | ||
| 1 |
2/3/2020
1:16 PM
|
Notice of Intended Case Filing | Request for Waiver of Rule 4 CSR 4.017(1) for ISRS Case Filings, or in the Alternative, Notice of Intended Case Filings |