Current Date/Time: 9/21/2025 12:28:29 AM
Docket Sheet
ER-99-247
Status
Closed (5/15/2000)
Utility Type
Electric
Type of Case
Rate Case (Large)
Subject Companies
Style of Case
In the Matter of St. Joseph Light & Power Company's Revised Electric Rate Schedules Designed to Increase Rates for Electrical Service in the Company's Missouri Service Territory
Assigned Judge
Assigned Attorney
Display Items:
-
Filter by Type of Filing:
Show Only:
or Hide:
Returning
95
/ 95
Filed on Behalf of | Response to Previous Filings | ||||
---|---|---|---|---|---|
95 |
5/3/2000
|
Order | Order Approving Tariffs in Compliance with Commission Order | ||
94 |
5/1/2000
|
Staff Recommendation | Staff Recommendation | ||
93 |
4/18/2000
|
Notice | Notice Reopening Case | ||
92 |
4/14/2000
|
Tariff | Tariff Sheets (200000949) | ||
91 |
10/20/1999
|
Order | Order Approving Tariffs Pursuant to Commission Order | ||
90 |
10/19/1999
|
Staff Recommendation | Staff Recommendation | ||
89 |
10/4/1999
|
Tariff | Substitute Tariff Sheets (200000164) | ||
88 |
8/27/1999
|
Tariff | Tariff (0000164) | ||
87 |
8/17/1999
|
Order | Order Approving Stipulation and Agreement | ||
86 |
8/5/1999
|
Notice | Notice Canceling Hearing on Stipulation and Agreement | ||
85 |
7/23/1999
|
Transcripts | Transcript - Volume 5 (Hearing - Jefferson City, MO - July 7, 1999) | ||
84 |
7/23/1999
|
Transcripts | Transcript - Volume 4 (Hearing - Jefferson City, MO - July 6, 1999) | ||
83 |
7/21/1999
|
Request | Request for Memorandum on Stipulation and Agreement | ||
82 |
7/16/1999
|
Stipulation and Agreement | Unanimous Stipulation and Agreement | ||
81 |
7/15/1999
|
Order | Order Granting Extension of Time | ||
80 |
7/14/1999
|
Motion | Motion | ||
79 |
7/12/1999
|
Notice | Notice of Hearing | ||
78 |
7/2/1999
|
Motion | Motion to Strike, or in the Alternative, Motion for Permission to File Supplemental Surrebuttal Testimony on Two Issues, and Supplemental Surrebuttal Testimony | ||
77 |
6/30/1999
|
Tariff | Corrected Schedule SMT-3-1 to the Surrebuttal Testimony of Steve M. Traxler | ||
76 |
6/30/1999
|
Transcripts | Transcript - Volume 3 (Public Hearing - St. Joseph, MO - June 16, 1999) | ||
75 |
6/24/1999
|
Statement of Position | Combined Statement of Position of AG Processing, Inc. a Cooperative, Friskies Petcare, a Division of Nestle USA, Wire Rope Corporation of America, and Quaker Oats Company | ||
74 |
6/24/1999
|
Other | Reconciliation (Staff) | ||
73 |
6/24/1999
|
Statement of Position | Staff's Statement of Position on Issues | ||
72 |
6/24/1999
|
Other | Reconciliation (SLJP) | ||
71 |
6/24/1999
|
Statement of Position | St. Joseph Light and Power Company Statement of Position on Disputed Issues | ||
70 |
6/24/1999
|
Statement of Position | Office of the Public Counsel's Statements of Position | ||
69 |
6/22/1999
|
Testimony | Surrebuttal Testimony (Brubaker) on Behalf of Industrial Consumers | ||
68 |
6/22/1999
|
Testimony | Surrebuttal Testimony (Bolin, Burdette, and HU) on Behalf of Office of the Public Counsel | ||
67 |
6/22/1999
|
Testimony | Surrebuttal Testimony (Stoll, Pullen, Rush, Wyble, Liechti, Swope, Weisensee, Allen, Fangman, Ferry, Modlin, and Cross) on Behalf of St. Joseph Light & Power Company | ||
66 |
6/22/1999
|
Testimony | Surrebuttal Testimony (Bible, Canady, McDuffey, Pyatte, Russo, Traxler and Watkins) (Harris and Lin HC & NP) on Behalf of Staff | ||
65 |
6/18/1999
|
Transcripts | Transcript - Volume 2 (Public Hearing - Maryville, MO - June 9, 1999) | ||
64 |
6/17/1999
|
Other | List of Issues, Order of Witnesses and Order of Cross-Examination | ||
63 |
6/14/1999
|
Order | Order Amending Procedural Schedule | ||
62 |
6/10/1999
|
Testimony | Rebuttal Testimony (Brubaker) on Behalf of Industrial Consumers | ||
61 |
6/10/1999
|
Testimony | Rebuttal Testimony (Trippensee, Kind, Burdette & HU) (Bolin HC & NP) on Behalf of Office of the Public Counsel | ||
60 |
6/10/1999
|
Testimony | Rebuttal Testimony (Bible, Harris, Lin, Proctor, Pyatte, Russo, Schwieterman, Traxler, Washburn, and Watkins) on Behalf of Staff | ||
59 |
6/10/1999
|
Testimony | Rebuttal Testimony (Allen, Cannell, Cross, Ferry, Liechti, Modlin, Pullen, Rush, Smith, Stoll, Svuba, Swope, Weisensee, and Wyble) on Behalf of St. Joseph Light & Power Company (Modlin & Ferry - HC) | ||
58 |
6/9/1999
|
Transcripts | Transcript - Volume 1 (Prehearing Conference - Jefferson City, MO - May 24, 1999) | ||
57 |
5/21/1999
|
Other | Advice of Joinder in Intervention (Quaker Oats Company) | ||
56 |
5/20/1999
|
Testimony | Direct Testimony (McDuffey, Pyatte, Ross, and Watkins) on Behalf of Staff | ||
55 |
5/20/1999
|
Testimony | Direct Testimony (Brubaker) on Behalf of Industrial Consumers | ||
54 |
5/20/1999
|
Testimony | Direct Testimony (HU) on Behalf of Office of the Public Counsel | ||
53 |
5/13/1999
|
Testimony | Direct Testimony of Graham Vesely, James D. Schwieterman, James M. Russo, Guy C. Gilbert, Lisa J. Canady, Dennis Patterson, Lena M. Mantle, Tom Y. Lin, Janice Pyatte, Ronald L. Bible, V. William Harris, David W. Elliott, Steve M. Traxler, Harris, Elliott and Traxler (HC) Harris, Elliott and Traxler | ||
52 |
5/13/1999
|
Other | Staff Accounting Schedules | ||
51 |
5/13/1999
|
Testimony | Direct Testimony of Mark Burdette, Russell W. Trippensee, and Kimberly K. Bolin on Behalf of Public Counsel (Bolin - HC & NP) | ||
50 |
5/13/1999
|
Testimony | Direct Testimony of Maurice Brubaker on Behalf of Industrial Consumers | ||
49 |
4/27/1999
|
Order | Order Scheduling Additional Local Public Hearing and Changing Time of Previously Scheduled Local Public Hearing | ||
48 |
4/19/1999
|
Non-Disclosure Agreement | Non-Disclosure Agreement of Maurice Brubaker | ||
47 |
4/9/1999
|
Request | Public Counsel's Request for Additional Local Public Hearings | ||
46 |
4/8/1999
|
Order | Order Scheduling Local Public Hearing | ||
45 |
3/5/1999
|
Order | Order Adopting Procedural Schedule | ||
44 |
2/28/1999
|
Order | Order Granting Intervention | ||
43 |
2/22/1999
|
Response | Staff's Response to Public Counsel's Procedural Schedule Recommendation | ||
42 |
2/17/1999
|
Other | Joint Industrial Intervenors Response to Public Counsel's Recommended Procedural Schedule | ||
41 |
2/17/1999
|
Order | Order Denying Motion to Dismiss, Granting Motion to Consolidate and Establishing Test Year | ||
40 |
2/16/1999
|
Response | Intervenor AG Processing, Inc. Response to Staff Motion to Consolidate | ||
39 |
2/16/1999
|
Other | Response of SJLP to Procedural Schedule Recommendation's of Staff and Public Counsel | ||
38 |
2/11/1999
|
Procedure Schedule | Public Counsel's Procedural Schedule Recommendation | ||
37 |
2/11/1999
|
Motion | Staff's Motion to Establish Procedural Schedule | ||
36 |
2/10/1999
|
Transcripts | Transcript - Volume 1 (Early Prehearing Conference - Jefferson City, MO - February 4, 1999) | ||
35 |
2/10/1999
|
Order | Order Denying Motion to Consolidate | ||
34 |
2/10/1999
|
Other | Public Counsel's Suggestions in Support of Staff's Motion to Consolidate and Suggestions in Opposition to St. Joseph Light & Power Company's Motion to Dismiss | ||
33 |
2/9/1999
|
Response | Response of SJLP to Staff's Motion to Consolidate Case Nos. EC-98-573 and ER-99-247 | ||
32 |
2/5/1999
|
Motion | Staff's Motion to Consolidate Case Nos. EC-98-573 and ER-99-247 | ||
31 |
2/2/1999
|
Other | SJLP's Suggestions in Opposition to Motion to Consolidate | ||
30 |
2/1/1999
|
Other | Staff's Suggestions in Support of Public Counsel's Motion to Consolidate | ||
29 |
1/29/1999
|
Notice | Notice of Correction | ||
28 |
1/26/1999
|
Application to Intervene | Late-Filed Application to Intervene of Friskies Petcare, A Division of Nestle USA | ||
27 |
1/25/1999
|
Motion | Motion to Consolidate on Behalf of the Office of the Public Counsel | ||
26 |
1/22/1999
|
Testimony | Direct Testimony (Steinbecker, Stoll, Svuba, Stuart, JR., Allen, Cross, Ferry, Liechti, Modlin, Pullen, Rush, Smith, Swope, Weisensee) on Behalf of St. Joseph Light & Power Company | ||
25 |
1/19/1999
|
Order | Order Directing Intervention | ||
24 |
1/14/1999
|
Order | Order Establishing Test Year, Establishing Date for Filing Direct Testimony and Schedules Early Prehearing Conference | ||
23 |
1/13/1999
|
Application to Intervene | Late-Filed Application to Intervene of Wire Rope Corporation of America, Inc. | ||
22 |
1/11/1999
|
Response | Reply to Staff's Response to SJLP's Reply to Staff's Motion to Establish Company's Direct Testimony Filing Date | ||
21 |
1/11/1999
|
Response | Staff's Response to SJLP's Reply to Staff's Motion to Establish Company's Direct Testimony Filed Date | ||
20 |
1/7/1999
|
Order | Order Granting Protective Order | ||
19 |
1/6/1999
|
Other | Support of Staff Motion to Establish Testimony Filing Date and Early Prehearing Conference | ||
18 |
1/6/1999
|
Response | Response by AG Processing, Inc. on Motion to Establish Test Year | ||
17 |
1/5/1999
|
Motion | Applicant's Motion for Issuance of Protective Order | ||
16 |
1/4/1999
|
Response | SLJP's Reply to Staff's Motion to Establish Company's Direct Testimony Filing Date | ||
15 |
12/29/1998
|
Response | Public Counsel's Response to St. Joseph Light & Power Company's Motion for Order Establishing Test Year | ||
14 |
12/24/1998
|
Other | Staff's Response to Objection of St. Joseph Light & Company | ||
13 |
12/24/1998
|
Motion | Staff's Motion to Establish Company's Direct Testimony Filing Date and to Schedule Early Prehearing Conference | ||
12 |
12/24/1998
|
Other | Staff's Response to Company's December 17, 1998 Reply | ||
11 |
12/22/1998
|
Order | Order Granting Intervention | ||
10 |
12/22/1998
|
Order | Suspension Order and Notice | ||
9 |
12/17/1998
|
Other | Objection of St. Joseph Light & Power Company | ||
8 |
12/17/1998
|
Response | SJLP's Reply to Staff's Response to Company's Motion for Order Establishing Test Year | ||
7 |
12/16/1998
|
Other | Reservation of Position by AG Processing , Inc. on Motion to Establish Test Year | ||
6 |
12/15/1998
|
Other | Substitute Page 2 for Page 2 of Staff's Response to Company's Motion for Order Establishing Test Year | ||
5 |
12/14/1998
|
Response | Staff's Response to Company's Motion for Order Establishing Test Year | ||
4 |
12/14/1998
|
Request | Request for Suspension of Rate Filing of AG Processing, Inc. | ||
3 |
12/14/1998
|
Application to Intervene | Application to Intervene of AG Processing, Inc. | ||
2 |
12/4/1998
|
Motion | Motion for Order Establishing Test Year on Behalf of St. Joseph Light & Power Company | ||
1 |
12/1/1998
|
Tariff | St. Joseph Light & Power Company's Revisions to Electric Rate Schedules Tariff Filed (9900427/Effective Date January 1, 1999) |