Current Date/Time: 5/2/2025 8:48:30 AM
Calendar Display
EA-2025-0028
Submission No.
Style of Case
In the Matter of the Application of Union Electric Company d/b/a Ameren Missouri for a Certificate of Convenience and Necessity to Construct, Own, Operate and Maintain a Transmission Substation in Cooper County, Missouri
Events
Responsible Party | |||||
---|---|---|---|---|---|
3/20/2025 | Report(s) |
|
The Staff of the Commission shall file a Report or Recommendation no later than March 20, 2025 | ||
3/20/2025 | Recommendation(s) |
|
The Staff of the Commission shall file a Report or Recommendation no later than March 20, 2025 | ||
2/24/2025 | Testimony |
|
Rebuttal | ||
2/12/2025 | Amended Application |
|
|||
2/3/2025 | Procedural Schedule |
|
The parties shall file a proposed procedural schedule or an alternative pleading no later than February 3, 2025. | ||
1/27/2025 | Filing(s) |
|
The parties shall file a proposed procedural schedule or an alternative pleading no later than January 27, 2025. | ||
1/27/2025 | Pleading |
|
The parties shall file a proposed procedural schedule or an alternative pleading no later than January 27, 2025. | ||
12/27/2024 | Procedural Schedule |
|
The parties shall file a proposed procedural schedule or an alternative pleading no later than December 27, 2024. | ||
11/26/2024 | Procedural Schedule |
|
The parties shall file a proposed procedural schedule or an alternative pleading no later than November 26, 2024. | ||
11/5/2024 | Application(s) to Intervene |
|
Applications to intervene shall be filed no later than November 5, 2024. | ||
6/20/2024 | Brief(s) |
|
Reply Briefs |