Current Date/Time: 5/6/2025 8:34:27 PM
Docket Sheet
EO-2009-0249
Status
Closed (6/25/2010)
Utility Type
Electric
Type of Case
Other
Subject Companies
Style of Case
In the Matter of the Consideration of Adoption of the PURPA Section 111(d)(16) Consideration of Smart Grid Investments Standard as Required by Section 1307 of the Energy Independence and Security Act of 2007.
Assigned Judge
- Stearley, Harold (Lead Judge)
Assigned Attorney
- Williams, Nathan (Lead Attorney)
- Dottheim, Steve
Related Submission No.
Consolidated To
Consolidated From
Data Request Contact Person
Display Items:
-
Filter by Type of Filing:
Show Only:
or Hide:
Returning
26
/ 26
Filed on Behalf of | Response to Previous Filings | ||||
---|---|---|---|---|---|
26 |
6/25/2010
4:13 PM
|
Other | Withdrawal of Counsel | ||
25 |
2/9/2009
3:21 PM
|
Order | Order Closing Dockets and Providing Direction for Future Filings | ||
24 |
2/6/2009
3:39 PM
|
Order | Order and Notice Regarding Classification of Dockets and Ex Parte Rule | ||
23 |
1/29/2009
11:09 AM
|
Order | Order Granting Applications To Intervene | ||
22 |
1/26/2009
1:38 PM
|
Notice | Notice Advising Parties How to Participate in Prehearing Conference by Telephone | ||
21 |
1/26/2009
9:16 AM
|
Order | Order Establishing A Deadline To Respond To late Intervention Requests | ||
20 |
1/23/2009
3:08 PM
|
Application to Intervene | Application of Midwest Independent Transmission System Operator, Inc. to Intervene | ||
19 |
1/22/2009
8:25 AM
|
Notice | Notice of Change of Room for Prehearing Conference | ||
18 |
1/20/2009
3:30 PM
|
Order | Order Granting Applications to Intervene | ||
17 |
1/16/2009
5:06 PM
|
Application to Intervene | Application of Kansas City Power & Light Company and KCP&L Greater Missouri Operations Company for Leave to Intervene | 2 | |
16 |
1/16/2009
3:45 PM
|
Application to Intervene | Application to Intervene of Wal-Mart Stores East, LP, and Sam`s East, Inc. | ||
15 |
1/16/2009
11:24 AM
|
Application to Intervene | Application to Intervene | ||
14 |
1/16/2009
11:22 AM
|
Application to Intervene | Application to Intervene | ||
13 |
1/16/2009
11:21 AM
|
Application to Intervene | Application to Intervene | ||
12 |
1/15/2009
3:39 PM
|
Other | Application to Intervene of The Missouri Industrial Energy Consumers | ||
11 |
1/15/2009
10:18 AM
|
Order | Order Establishing A Deadline To Respond To Intervention Requests | ||
10 |
1/13/2009
1:56 PM
|
Application to Intervene | Application of Union Electric Company, d/b/a AmerenUE to Intervene | 2 | |
9 |
1/9/2009
8:39 AM
|
Application to Intervene | Application of Southwest Power Pool, Inc. to Intervene | 2 | |
8 |
1/8/2009
9:55 AM
|
Application to Intervene | Missouri Department of Natural Resources` Application to Intervene | ||
7 |
1/5/2009
7:49 PM
|
Response to Order | Staff Response To Order Directing The Commission`s Staff To Show Cause As To Why The Above Captioned Cases Should Not Be Reclassified As Workshop Cases | ||
6 |
12/29/2008
10:34 AM
|
Application to Intervene | Application to Intervene | ||
5 |
12/22/2008
2:23 PM
|
Order | Order Directing The Commission's Staff To Show Cause As To Why The Above Captioned Cases Should Not Be Reclassified As Workshop Cases | ||
4 |
12/22/2008
11:06 AM
|
Notice | Notice of Correction | ||
3 |
12/19/2008
4:32 PM
|
Application to Intervene | Dogwood Energy, LLC`s Application to Intervene | ||
2 |
12/17/2008
10:30 AM
|
Order | Order Establishing Cases, Directing Notice, Establishing A Deadline For Submission of Intervention Requests, Setting a Prehearing Conference and Setting Date For Filing Procedural Schedules | ||
1 |
12/15/2008
1:11 PM
|
Motion | Motion To Establish A Case, Provide Notice And Schedule A Prehearing Conference |